Show More


Posts occurring in May 2014

The "Old" Fitness Center: Demolition Phase Moves Quickly

May 27, 2014

With the end of the academic year, the "old" fitness center in the Lilly Center quickly moved into demolition phase.  The space occupied by what used to be the fitness center and workout space will become a set of multi-purpose rooms for spin class, fitness groups, and dance, among other activities. 

Over the course of the last few days, the old fitness equipment has been removed and demolition is well underway.  Until the new Welch Fitness Center opens in August, a temporary workout space has been set up in the Indoor Tennis and Track Center. 

The view from the "old" hallway outside the fitness center on the lower level of the original Lilly Center.


A view from the former free weight section of the Lilly Center fitness center.

Continue Reading


Lilly Center: Wood Ceiling Goes in Lobby, Work Begins on Renovation

May 21, 2014

The wood ceiling of the lobby in the expanded Lilly Center is nearing completion this week, as crews continue to make progress on the interior finishes of the building. With classes coming to an end for the academic year, crews have also shifted their focus to the renovation of some existing spaces within the building. 

Work continues on the lobby of the renovated and expanded Lilly Center. The wood ceiling is being installed as crews work on the main staircase and complete drywall. 

As of Tuesday morning, crews had already begun initial demolition on the hallway just outside the former fitness center within the Lilly Center. Renovations along this hallway will make room for updated recreational locker rooms, and for the repurposing of the fitness center space into multi-purpose rooms for dance, spin classes and other activities. 

Continue Reading


Construction Update: Lilly and Hoover Hall

May 19, 2014

In a recent note to campus, Associate Vice President for Facilities Dick Vance offered an update on ongoing construction activity at the Lilly Center and the soon-to-begin construction activity at the site of Hoover Hall. The full text of his note to campus is below:

Dear Faculty, Staff and Students,

As we swiftly approach the end of the academic year, we write to update you on the logistics of two of our major capital projects: continued construction at the Lilly Center and the beginning of construction of Hoover Hall, which was formally approved during last week’s meeting of the Board of Trustees.

Lilly Center Construction: Fitness Equipment to Re-Locate Temporarily

We are entering the final period of construction on the addition at the Lilly Center, with our target of opening the new facility in August. Beginning Monday, May 19, the Lilly Center—including the fitness center—will close to allow necessary construction and renovation activity to be completed. The Lilly Center will...

Continue Reading


Hoover Hall Construction is Under Way

May 19, 2014

After months of planning and preparation, the construction process at the site of Hoover Hall -- the University's new dining hall -- is now underway. 

From Saturday's announcement:

Construction efforts at the site of Hoover Hall, the University’s new 48,600 square-foot dining hall, are officially under way following a commencement weekend groundbreaking ceremony in the shadow of East College.

The new hall will fulfill a core element of the University’s Campus Master Plan, which was approved by the Board of Trustees in October of 2010 and called for the transformation of the campus core into a place of greater connection, contemplation, and creativity. Hoover Hall, which will sit just north of Hanna Street along Burkhart Walk, will replace the current “Hub,” a food-court-style dining hall in the Memorial Student Union Building, and will serve as the primary dining space for first-year students and upper-class students living in University housing.

Many of those who have helped make...